"A significant portion of the U.S. missile defense capability was wiped out during the summer of 2006 because torrential rains caused ground-based interceptor silos to be damaged by flood waters," POGO said in a statement.

"Boeing, the contractor that is at least partly responsible for failing to protect the silos, will most likely still receive an estimated $38 million to repair the silos and a $100 million no-bid contract to build more silos. Boeing would also receive a $7 million award fee added to the contract," the group said.

POGO noted that "the flooding occurred during a three-week period between the end of June and early July 2006 when Ft. Greely received several inches of rain. Ft. Greely and Vandenberg Air Force Base in California house the nation's only Missile Defense Agency interceptor missiles."

"The flooding damaged 25 percent of the U.S. interceptor missiles' launch capability. These silos house the interceptor missiles that would be used to attempt to intercept a missile aimed at the United States. No interceptors were in the flooded silos," the group's report said.

POGO also reported that the flooding debacle had set off a fierce row between the U.S. military and Boeing, the prime contractor for building the Fort Greely interceptor fields.